A data centre exit is a programme, not a single migration, and most of its cost is set by your own contracts rather than by a price list. The table separates the lines with a public rate from the ones you have to get from your own bills and quotes.
Data centre exit cost lines (AWS rates read 26 November 2026)
| Cost line | Published rate | Who sets the price |
|---|---|---|
| Online data copy (AWS DataSync) | $0.0125 per GB Basic; $0.015 per GB + $0.55 per task run Enhanced | AWS |
| Private link into AWS (Direct Connect) | Port $0.30 an hour (1 Gbps) or $2.25 an hour (10 Gbps); data in $0.00 per GB | AWS, plus your carrier and colocation |
| Offline transfer device (Snowball Edge) | Existing customers only; see our Snowball page | AWS |
| Facility or colocation while both estates run | Not published: your monthly bill | Your landlord or colocation contract |
| Cloud run cost during the overlap | Per-service list prices; price your target estate | AWS, Microsoft or Google |
| Migration labour | Not published: quoted per server or per wave | Your partner or in-house team |
| Decommissioning and asset disposal | Not published: quoted per asset | Your ITAD vendor |
Two of those lines are usually small next to the others. The overlap is the one that grows: the facility bill keeps running until the last rack is empty, and the cloud bill starts with the first wave, so every month both run is paid twice.
The transfer lines below use AWS's published rates. Everything else starts at zero: enter your current monthly facility or colocation bill, your cloud estimate for the migrated estate, and the per-server and per-asset prices from your quotes.
The transfer is the line people ask about first, and at AWS's rates it is small. For 500 TB copied online into Amazon S3 (512,000 GB, using the 1,024 GB per TB that AWS uses in its own pricing examples):
500 TB into AWS over Direct Connect, AWS list prices read 26 November 2026
| Line | Arithmetic | Cost |
|---|---|---|
| DataSync, Basic mode | 512,000 GB x $0.0125 | $6,400 |
| DataSync, Enhanced mode (alternative) | 512,000 GB x $0.015, plus $0.55 per task run | $7,680 |
| Direct Connect 10 Gbps port, held 720 hours | 720 x $2.25 | $1,620 |
| Direct Connect 1 Gbps port, held 720 hours (alternative) | 720 x $0.30 | $216 |
| Data transfer in over Direct Connect | $0.00 per GB | $0 |
Not in the table: S3 request and storage charges (DataSync bills them at standard rates), the cross-connect in your colocation facility and the carrier circuit to the Direct Connect location, which your colocation provider and carrier price. Time sets the port choice more than price does. At the full 10 Gbps line rate, 500 decimal terabytes take 400,000 seconds, about 4.6 days of continuous transfer; at 1 Gbps, about 46 days. Real throughput is lower than line rate, so measure it on a test copy and hold the port for as long as the copy and the final sync need.
AWS Snowball Edge, the offline route, is open only to existing customers; AWS closed it to new ones on 7 November 2025. Its per-job prices and the break-even against the network are on the AWS Snowball cost page, and the per-GB detail is on the AWS DataSync pricing page.
The largest public record of data centre exits is the US federal government's Data Center Optimization Initiative, which the Government Accountability Office reviews. Its February 2023 report, GAO-23-105946, gives these agency-reported figures for the 24 participating agencies:
Federal data centre closures and reported savings, GAO-23-105946 (February 2023)
| Measure | Figure | Period |
|---|---|---|
| Data centres open at the start of the year, 24 agencies | 1,746 (Defense 638, Veterans Affairs 274) | Start of FY2022 |
| Data centres closed | 58 | FY2021 |
| Reported cost savings (22 of 24 agencies met their goals) | $612.326 million | FY2021 |
| Data centres closed, with 58 more planned | 20 | FY2022, to August 2022 |
| Reported cost savings identified | $334.324 million | FY2022, to August 2022 |
| Cumulative cost savings and avoidances | $6.6 billion | FY2012 to FY2021 |
What these figures are, and are not
Wave migration splits the estate into batches grouped by dependency, moves one batch, validates it and moves on. AWS, Microsoft and Google each describe a version of it in their cloud adoption guidance. Its effect on cost runs through the overlap line: the cloud bill rises wave by wave, but the facility bill only falls when you can hand back a whole contract unit (a cage, a suite, a power commitment), and in an owned building only when the building is empty. Plan the waves so that whole units empty together, and the overlap months in the calculator are the ones you can actually shorten.
Most enterprise estates sit in colocation, on multi-year terms. Read the contract for four things before you set the programme dates: the term end, the notice period for non-renewal, any clause that lets you reduce space or power during the term, and the early-termination charge. A programme that finishes after the term end usually pays for a renewal it does not need; one that finishes early pays for space it has emptied unless the contract lets it step down. Your monthly bill and the months of overlap are the two inputs the calculator needs.
Every server, storage array and switch that held data needs it removed before the hardware leaves your control, and the disposal needs a paper trail for audit. IT asset disposition (ITAD) vendors quote per asset, per drive or per pallet, and may net a resale credit for newer equipment against the fee. Ask for:
The final workloads are usually the hardest to move: applications nobody actively develops, vendor software not supported on the target cloud, or systems tied to specific hardware. Because the facility cannot close until they leave, they hold the whole overlap open. The usual answers are to move them to a small colocation or hosted footprint so the main site can close, to retire them, or to fund their rework as a separate project. Price each option against the monthly facility bill it would let you stop.
A. No cloud provider, integrator or colocation company publishes a price for a data centre exit, because most of the cost is your own: the facility or colocation bill for the months both estates run, the cloud bill over the same months, a partner's per-server quote and a disposal vendor's per-asset quote. The lines that do have published rates are the transfer ones. AWS DataSync charges $0.0125 per GB in Basic mode and $0.015 per GB plus $0.55 per task run in Enhanced mode; an AWS Direct Connect port costs $0.30 an hour at 1 Gbps or $2.25 an hour at 10 Gbps, and data transfer in over Direct Connect is $0.00 per GB (AWS pricing pages, read 26 November 2026). The calculator on this page adds your own numbers to those rates line by line.
A. At AWS's published rates, copying 500 TB (512,000 GB, using the 1,024 GB per TB that AWS uses in its own examples) with DataSync costs $6,400 in Basic mode or $7,680 plus $0.55 per task run in Enhanced mode. Holding a 10 Gbps Direct Connect port for 720 hours adds $1,620; data transfer in over Direct Connect is $0.00 per GB. S3 request and storage charges, the cross-connect and the carrier circuit are extra. At the full 10 Gbps line rate 500 TB takes about 4.6 days of continuous transfer; at 1 Gbps about 46 days, so measure your real throughput before you size the port.
A. The US Government Accountability Office's February 2023 review of the Data Center Optimization Initiative (GAO-23-105946) reports that federal agencies closed 58 data centres in fiscal year 2021, and that 22 of the 24 agencies met their cost savings goals that year, identifying $612.326 million in savings. Agencies reported a cumulative $6.6 billion in cost savings and avoidances from fiscal years 2012 through 2021. GAO notes it did not independently validate the agencies' reported savings, and these are savings, not the cost of the migrations.
A. IT asset disposition (ITAD) vendors quote it per asset, per drive or per pallet, depending on whether drives are wiped, shredded or the equipment is resold; we have not found a published rate card from a major vendor, so get the price on a quote for your own asset list. Ask for a certificate of sanitization per device that names the method used against NIST SP 800-88 (Guidelines for Media Sanitization), a serial-level asset report, and any resale credit netted against the fee. Enter the per-asset quote in the calculator on this page.
A. As long as the last workload in the building. The duration matters to the budget because the facility or colocation bill keeps running until the final rack is out, and the cloud bill starts with the first wave, so every month of overlap is paid twice. The public record shows how easily a final step slips: in fiscal year 2021 the Department of Justice missed its data centre closure goal because it delayed the final step of migrating one data centre to a cloud provider into fiscal year 2022, to keep it clear of its year-end closeout (GAO-23-105946).
A. The final workloads in a data centre exit are usually the hardest to move: applications nobody actively develops, vendor software not supported on the target cloud, or systems tied to specific hardware. Because the facility cannot close until they leave, they hold the whole overlap open. Programmes either move them to a small colocation or hosted footprint and close the main site, retire them, or fund their rework separately, so that a handful of systems does not keep the full facility bill running.
On-prem to AWS ->
MAP credits, EC2, Snowball
On-prem to Azure ->
Hybrid Benefit, FastTrack
On-prem to GCP ->
Sustained-use, BigQuery
AWS DataSync pricing ->
Per-GB rates and extra charges
AWS Snowball cost ->
Per-job prices, existing customers
100-server worked scenario ->
Mid-market reference build
Lift-and-shift per server ->
Per-server cost lines
VMware to cloud ->
Post-Broadcom licence flight
Mainframe modernisation ->
GAO-reported costs, AWS runtime rates
10 hidden costs ->
Detailed playbook
Updated 26 November 2026