Data centre to cloud migration cost, 2026

Nobody publishes a price for a data centre exit. Most of it is your own facility bill for the months both estates run, plus quotes for the migration labour and the hardware disposal. The transfer lines do have published rates: AWS DataSync copies data at $0.0125 per GB and a 10 Gbps Direct Connect port costs $2.25 an hour, with data in at $0.00 per GB (AWS pricing pages, read 26 November 2026). Below: those rates, a worked 500 TB transfer, the US federal closure record, and a calculator for your own numbers.

The cost lines, and which ones have a published price

A data centre exit is a programme, not a single migration, and most of its cost is set by your own contracts rather than by a price list. The table separates the lines with a public rate from the ones you have to get from your own bills and quotes.

Data centre exit cost lines (AWS rates read 26 November 2026)

Cost linePublished rateWho sets the price
Online data copy (AWS DataSync)$0.0125 per GB Basic; $0.015 per GB + $0.55 per task run EnhancedAWS
Private link into AWS (Direct Connect)Port $0.30 an hour (1 Gbps) or $2.25 an hour (10 Gbps); data in $0.00 per GBAWS, plus your carrier and colocation
Offline transfer device (Snowball Edge)Existing customers only; see our Snowball pageAWS
Facility or colocation while both estates runNot published: your monthly billYour landlord or colocation contract
Cloud run cost during the overlapPer-service list prices; price your target estateAWS, Microsoft or Google
Migration labourNot published: quoted per server or per waveYour partner or in-house team
Decommissioning and asset disposalNot published: quoted per assetYour ITAD vendor

Two of those lines are usually small next to the others. The overlap is the one that grows: the facility bill keeps running until the last rack is empty, and the cloud bill starts with the first wave, so every month both run is paid twice.

Calculator: your exit, line by line

The transfer lines below use AWS's published rates. Everything else starts at zero: enter your current monthly facility or colocation bill, your cloud estimate for the migrated estate, and the per-server and per-asset prices from your quotes.

Data centre exit calculator

Your exit, line by line

The transfer lines use AWS's published rates. The rest start at zero: enter your own bill, estimate and quotes. Every sum is shown so you can redo it.

Data and network (published rates)
Overlap (your numbers)
Quotes (your numbers)

Data copy (AWS DataSync) AWS rate

500 TB x 1,024 GB x $0.0125

$6,400

Direct Connect port (data in is $0.00 per GB) AWS rate

730 port-hours x $2.25

$1,643

Facility or colocation bill while both estates run Your bill

12 months x $0

$0

Cloud run cost during the overlap Your estimate

12 months x $0

$0

Migration labour Your quote

0 servers x $0

$0

Decommissioning and asset disposal (ITAD) Your quote

0 assets x $0

$0

Contingency: 0% x $8,043 = $0

Total

$8,043

AWS rates from the DataSync and Direct Connect pricing pages, read 26 November 2026. DataSync rates are the ones in AWS's US East (Ohio) examples; Direct Connect port-hours are the same at every location except Japan. Not included: S3 request and storage charges, the cross-connect and carrier circuit to the Direct Connect location, data transfer out of AWS ($0.02 per GB to US locations over Direct Connect), and anything your contracts add.

Worked example: the network cost of moving 500 TB

The transfer is the line people ask about first, and at AWS's rates it is small. For 500 TB copied online into Amazon S3 (512,000 GB, using the 1,024 GB per TB that AWS uses in its own pricing examples):

500 TB into AWS over Direct Connect, AWS list prices read 26 November 2026

LineArithmeticCost
DataSync, Basic mode512,000 GB x $0.0125$6,400
DataSync, Enhanced mode (alternative)512,000 GB x $0.015, plus $0.55 per task run$7,680
Direct Connect 10 Gbps port, held 720 hours720 x $2.25$1,620
Direct Connect 1 Gbps port, held 720 hours (alternative)720 x $0.30$216
Data transfer in over Direct Connect$0.00 per GB$0

Not in the table: S3 request and storage charges (DataSync bills them at standard rates), the cross-connect in your colocation facility and the carrier circuit to the Direct Connect location, which your colocation provider and carrier price. Time sets the port choice more than price does. At the full 10 Gbps line rate, 500 decimal terabytes take 400,000 seconds, about 4.6 days of continuous transfer; at 1 Gbps, about 46 days. Real throughput is lower than line rate, so measure it on a test copy and hold the port for as long as the copy and the final sync need.

AWS Snowball Edge, the offline route, is open only to existing customers; AWS closed it to new ones on 7 November 2025. Its per-job prices and the break-even against the network are on the AWS Snowball cost page, and the per-GB detail is on the AWS DataSync pricing page.

The public record: US federal data centre closures

The largest public record of data centre exits is the US federal government's Data Center Optimization Initiative, which the Government Accountability Office reviews. Its February 2023 report, GAO-23-105946, gives these agency-reported figures for the 24 participating agencies:

Federal data centre closures and reported savings, GAO-23-105946 (February 2023)

MeasureFigurePeriod
Data centres open at the start of the year, 24 agencies1,746 (Defense 638, Veterans Affairs 274)Start of FY2022
Data centres closed58FY2021
Reported cost savings (22 of 24 agencies met their goals)$612.326 millionFY2021
Data centres closed, with 58 more planned20FY2022, to August 2022
Reported cost savings identified$334.324 millionFY2022, to August 2022
Cumulative cost savings and avoidances$6.6 billionFY2012 to FY2021

What these figures are, and are not

They are savings the agencies reported, not what their migrations cost, and GAO states that it did not independently validate them. They show the size of the prize a government estate has recorded from closing facilities, not a price per server. One line in the report is a cost lesson in itself: the Department of Justice missed its fiscal year 2021 closure goal because it delayed the final step of migrating one data centre to a cloud provider into the next fiscal year, to keep it clear of year-end closeout.

Wave planning: what it does to the cost

Wave migration splits the estate into batches grouped by dependency, moves one batch, validates it and moves on. AWS, Microsoft and Google each describe a version of it in their cloud adoption guidance. Its effect on cost runs through the overlap line: the cloud bill rises wave by wave, but the facility bill only falls when you can hand back a whole contract unit (a cage, a suite, a power commitment), and in an owned building only when the building is empty. Plan the waves so that whole units empty together, and the overlap months in the calculator are the ones you can actually shorten.

Colocation contract exit

Most enterprise estates sit in colocation, on multi-year terms. Read the contract for four things before you set the programme dates: the term end, the notice period for non-renewal, any clause that lets you reduce space or power during the term, and the early-termination charge. A programme that finishes after the term end usually pays for a renewal it does not need; one that finishes early pays for space it has emptied unless the contract lets it step down. Your monthly bill and the months of overlap are the two inputs the calculator needs.

Hardware decommissioning and asset disposal

Every server, storage array and switch that held data needs it removed before the hardware leaves your control, and the disposal needs a paper trail for audit. IT asset disposition (ITAD) vendors quote per asset, per drive or per pallet, and may net a resale credit for newer equipment against the fee. Ask for:

The last workload problem

The final workloads are usually the hardest to move: applications nobody actively develops, vendor software not supported on the target cloud, or systems tied to specific hardware. Because the facility cannot close until they leave, they hold the whole overlap open. The usual answers are to move them to a small colocation or hosted footprint so the main site can close, to retire them, or to fund their rework as a separate project. Price each option against the monthly facility bill it would let you stop.

How to reduce data centre exit cost

  1. Align the last wave with the colocation term end, or negotiate a step-down clause before the programme starts.
  2. Retire before you migrate: every workload switched off is one fewer to move, test and run twice.
  3. Plan waves so whole cages, suites or power commitments empty together; the facility bill only falls when a contract unit is handed back.
  4. Size the network from a measured test copy, not line rate, and hold the Direct Connect port only as long as the copy and final sync need.
  5. Move the long tail out of the main facility early so it does not hold the whole site open.
  6. Get ITAD quotes on your own asset list and compare them net of resale credit.
Q&A

Frequently asked

Q. How much does a full data centre to cloud migration cost?

A. No cloud provider, integrator or colocation company publishes a price for a data centre exit, because most of the cost is your own: the facility or colocation bill for the months both estates run, the cloud bill over the same months, a partner's per-server quote and a disposal vendor's per-asset quote. The lines that do have published rates are the transfer ones. AWS DataSync charges $0.0125 per GB in Basic mode and $0.015 per GB plus $0.55 per task run in Enhanced mode; an AWS Direct Connect port costs $0.30 an hour at 1 Gbps or $2.25 an hour at 10 Gbps, and data transfer in over Direct Connect is $0.00 per GB (AWS pricing pages, read 26 November 2026). The calculator on this page adds your own numbers to those rates line by line.

Q. What does it cost to move 500 TB to the cloud over the network?

A. At AWS's published rates, copying 500 TB (512,000 GB, using the 1,024 GB per TB that AWS uses in its own examples) with DataSync costs $6,400 in Basic mode or $7,680 plus $0.55 per task run in Enhanced mode. Holding a 10 Gbps Direct Connect port for 720 hours adds $1,620; data transfer in over Direct Connect is $0.00 per GB. S3 request and storage charges, the cross-connect and the carrier circuit are extra. At the full 10 Gbps line rate 500 TB takes about 4.6 days of continuous transfer; at 1 Gbps about 46 days, so measure your real throughput before you size the port.

Q. How much did US federal agencies save by closing data centres?

A. The US Government Accountability Office's February 2023 review of the Data Center Optimization Initiative (GAO-23-105946) reports that federal agencies closed 58 data centres in fiscal year 2021, and that 22 of the 24 agencies met their cost savings goals that year, identifying $612.326 million in savings. Agencies reported a cumulative $6.6 billion in cost savings and avoidances from fiscal years 2012 through 2021. GAO notes it did not independently validate the agencies' reported savings, and these are savings, not the cost of the migrations.

Q. What does hardware decommissioning cost?

A. IT asset disposition (ITAD) vendors quote it per asset, per drive or per pallet, depending on whether drives are wiped, shredded or the equipment is resold; we have not found a published rate card from a major vendor, so get the price on a quote for your own asset list. Ask for a certificate of sanitization per device that names the method used against NIST SP 800-88 (Guidelines for Media Sanitization), a serial-level asset report, and any resale credit netted against the fee. Enter the per-asset quote in the calculator on this page.

Q. How long does a full data centre exit take?

A. As long as the last workload in the building. The duration matters to the budget because the facility or colocation bill keeps running until the final rack is out, and the cloud bill starts with the first wave, so every month of overlap is paid twice. The public record shows how easily a final step slips: in fiscal year 2021 the Department of Justice missed its data centre closure goal because it delayed the final step of migrating one data centre to a cloud provider into fiscal year 2022, to keep it clear of its year-end closeout (GAO-23-105946).

Q. What is the last workload problem?

A. The final workloads in a data centre exit are usually the hardest to move: applications nobody actively develops, vendor software not supported on the target cloud, or systems tied to specific hardware. Because the facility cannot close until they leave, they hold the whole overlap open. Programmes either move them to a small colocation or hosted footprint and close the main site, retire them, or fund their rework separately, so that a handful of systems does not keep the full facility bill running.